‌Detailed Steps for Air Receiver Blowdown Operation

Release Time:2025.04.12 Browse:11

II. Drainage Procedure

  1. Pressure Relief

    • Gradually open the drain valve’s outlet to release pressure in stages until reaching a safe range (typically ≤0.2 MPa).

    • For dual-valve systems: Open the first valve to discharge liquid, close it, then open the second valve alternately until completion.

  2. Waste Discharge

    • Direct the drainage pipe to a safe area (e.g., explosion-proof container). Never discharge directly onto the ground .

    • Slowly open the bottom drain valve. Monitor the discharged material (color, odor). Stop immediately and report if oil, rust, or liquefied gas residues are detected .

    • Keep the valve open until no liquid flows to avoid splashing from rapid opening .

  3. Valve Reset

    • Close the drain valve and outlet sequentially. Check for leaks (e.g., tactile inspection for hissing sounds) .

    • Reopen the intake valve and gradually pressurize to normal operating pressure while monitoring gauge stability .